2. Design Stage
| Classification |
CM work of design stage |
| Project Management |
Establishment of standard and procedure of designer selection
Designer selection and writing contract documents
Advice and support for various approval work
Support Project Financing
Establishment of Project Management Information System(PMIS)
Supervision of various meetings
|
| Design Management |
Design Schedule Management
Check whether to reflect design documents of owner's requirements
Check coincidence of design documents of each field
Constructability review
|
| Prime Cost Management |
Project Cost Management Plan Establishment
Calculation of costs at each design stage-> Comparison to project budget-> Suggestion alternatives when it is exceeded or insufficient
VE(Value Engineering)
|
Construction Process Management |
Master Schedule Adjustment in Design Progress Stage
Construction Schedule Plan Establishment
Grasp Critical Path
Judgment of possibility of construction duration reduction through application of Fast Track
Establishment of Long Lead Item Procurement Method
|
| Quality/Safety Management |
Quality/Safety Design standard establishment
Quality/Safety management object and procedure stipulation
Check coincidence between design documents and quality/safety design standard
|
| Administrative Work |
Writing and reviewing design documents, approval procedure establishment
Design documents management standard establishment
|